TEG provided project engineering from concept through to final commissioning of the Dough Room and Ingredients Delivery.

  • 7 horizontal jacketed mixers
  • Flour silo and flour reticulation
  • Sugar silo and sugar
  • Water delivery
  • Melted fat system
  • including steam, chilled water, hot water, potable water
  • Total project value was $ 4.0m

Results

The project was delivered on time and achieved the required benefits. A highly automated ingredients delivery system that allowed efficient mixing processing on six production lines has been installed.